1. Overview
A workflow's Overview tab spells out its And once answered logic in plain language. In this environment's Contract: 1.1 Employee Approval workflow, setting the Owner Approval task to Task Complete sets u_OwnerApprovalStatus to Completed and Status_ID to 57 (Manager Approval), while setting it to Rejected sets Status_ID to 1 — each possible task answer can drive its own distinct field updates. These rules are managed per task from the workflow's Tasks tab.
2. Key Elements
- And once answered, on a workflow's Overview tab, lists every field update tied to a specific task answer.
- Different answers can update different fields — Status_ID on complete/reject in the example, plus a custom field (u_OwnerApprovalStatus) on complete. One answer can drive several updates.
- The answers a task can be given (for example, Task Complete, Rejected, Submission Completed/Generate Template) are chosen under Answers to offer in the task's How it finishes section.
- The field updates themselves live in the task's rules panel, What happens when "task" is answered → Change a field on the record, opened from the two-arrow icon beside the task on the Tasks tab. The When answered column shows how many field changes each task has.
- A field update here is what can trigger the next workflow in a chain, since other workflows can condition on that same field.
- The Workflow Flow diagram color-codes these as green (field update, complete) and red (field update, reject) boxes branching off the task node.
3. Viewing a Workflow's Field Updates
- From the Contract Insight homepage, click the Administration (sliders) icon at the bottom of the left navigation bar, search for workflow, and click Workflows.
- Find the workflow (for example, search 1.1 Employee Approval) and click its row to expand it.
- On the Overview tab, read And once answered — one line per field update, in the form "When task is set to answer, field becomes value."
.png)

4. Choosing the Answers a Task Offers
A field update can only fire on an answer the task actually offers, so set the answers first.
- Click the workflow's Tasks tab and click Edit on the task.
- Scroll to How it finishes.
- Under Answers to offer, tick each answer the assignee can choose (for example, Task Complete and Rejected).
- Click Save task.

5. Opening a Task's Field Update Rules
- On the Tasks tab, click the two-arrow (rules for what happens when this task is answered) icon beside the task's Edit button.
- The What happens when "task" is answered panel lists each rule under Change a field on the record, for example "When it's set to Task Complete - set Status_ID to 57."
- Use Edit or the trash icon on a rule to change or remove it. The same panel also offers Generate a document on an answer.

6. Adding or Editing a Field Update
- In the rules panel, click Add a field change (or Edit on an existing rule).
- In When the task is set to, choose the answer that triggers the update (for example, Task Complete or Rejected).
- On shows the record the field belongs to (for example, Contract Details).
- In Set this field, choose the field to change (for example, Status).
- In To, choose or enter the new value (for example, Manager Approval).
- Click Save change. Repeat for each answer that should update a field — a Task Complete rule and a Rejected rule are separate entries.


7. Viewing Field Updates in the Workflow Diagram
- On the workflow's Overview tab, click See it as a diagram.
- Green When task complete boxes and red When rejected boxes branch off the Task node, one per field update.
- A dashed line to a Next step box shows a workflow that the update can start.
.jpg)
8. Quick Reference Summary
| Task | How to Complete It |
|---|---|
| See a workflow's field updates | Administration → Workflows → expand → Overview → And once answered. |
| Choose the answers a task offers | Tasks → Edit → How it finishes → Answers to offer → Save task. |
| Open a task's field update rules | Tasks → two-arrow rules icon. |
| Add a field update on complete or reject | Rules panel → Add a field change → answer / field / value → Save change. |
| Change or remove a field update | Rules panel → Edit or trash icon. |
| See the updates visually | Overview → See it as a diagram. |